Operation & Maintenance

INTRODUCTION

Proyek Pipanisasi ini untuk Memenuhi kebutuhan Konsumen PT. Aneka Bumi Pratama terhadap PT. Mitra Energi Buana, agar mendapatkan pasokan gas melalui tie-in point jalur pipa gas (di LBCV Musi-2)  ke pabrik Aneka Bumi Pratama

Project         : EP & C – PIPELINE & PIPING FABRICATION.
Works           : Jasa Pekerjaan Pipanisasi 6300 meter, dan Piping Fabrication (Gas Metering Systems di Musi-2 area dan ABP area)
Owner           : PT. MITRA ENERGI BUANA.
Wo / Po.No. : –
Main-Con     : PT. VEROJASA TECHNICAL.
Sub-Con       : –
Role in Project : Main contractor

SCOPE OF WORK :

  1. Engineering (Design Drawing & As-built Drawing)
  2. Preparation (Manpower, Temporary Facility, Mob-Demob for Equipment, & Tools).
  3. Pipeline work : Pipeline dia-4 inch, Musi-2 – ABP 6300 meters.
  4. Piping work : Piping Fabrication Gas Metering Systems Musi-2 area & GMS PT. ABP area (Including Material as per specification and drawings.
  5. Hydro Testing, Equipment, Consumables & Manpower, Cleaning, Flushing Blowing & Drying Equipment, Bolt Tightening
  6. Piping Install.
  7. Tie-in (Musi-2).
  8. N2 Purging, Gas-in  & Start-up